AC•THOR 9s – Operation with 3 single-phase heating elements
Our "Support" section offers many practical tips that will help you with the installation and commissioning of our devices.
The load control of 3 single-phase heating elements is a special form of operating mode M1 for hot water.
CAUTION:
This is to be clearly distinguished from operating mode M2 "Layer Charging," where load control is switched to another 3-phase consumer using an external opener and a closer!
The following instructions from the operating manual are important:
Solution
The regular operation for 3 single-phase heating elements can be set with a single adjustment. Simply switch the "Load Priority" accordingly under "Settings" (gear symbol).
Wist u dat?
Tip: Connect the topmost heating element to the control output OUT-3 of the AC•THOR 9s. If you accidentally did not follow the order, simply switch the consumption plugs. This saves rewiring!
More articles
Bedrijf
Nieuwe prijzen voor my-PV-producten per 1 juli 2026Door stijgende personeels-, materiaal- en productiekosten is een prijsaanpassing nodig.
Lees meer...Algemeen
my-PV bij Intersolar 2026Van 23 tot 25 juni 2026 zal Intersolar Europe in München opnieuw haar deuren openen – en my-PV zal er ook zijn.
Lees meer...Referenties
Duitse meester elektricien met een zonne-energiebestendig bedrijfspandEen zonne-energiebedrijf uit Neder-Franken verwarmt zijn bedrijfsgebouw met continu gereguleerde PV-elektriciteit.
Lees meer...