AC•THOR 9s – Operation with 3 single-phase heating elements

Our "Support" section offers many practical tips that will help you with the installation and commissioning of our devices.

The load control of 3 single-phase heating elements is a special form of operating mode M1 for hot water.

CAUTION:

This is to be clearly distinguished from operating mode M2 "Layer Charging," where load control is switched to another 3-phase consumer using an external opener and a closer!

The following instructions from the operating manual are important:

Solution

The regular operation for 3 single-phase heating elements can be set with a single adjustment. Simply switch the "Load Priority" accordingly under "Settings" (gear symbol).

Cose da sapere

Tip: Connect the topmost heating element to the control output OUT-3 of the AC•THOR 9s. If you accidentally did not follow the order, simply switch the consumption plugs. This saves rewiring!

More articles

Partner

Using my-PV products with Zendure balcony power plants

No more giving away surplus electricity for free – use it for water heating instead!

Leggi di più...

Generale

La mia partecipazione a KEY ENERGY 2025 in Italia

Anche quest'anno, my-PV sarà presente a KEY ENERGY 2025 in Italia.

Leggi di più...

Partner

New compatibility: my-PV and Forstner Speichertechnik

With the compatibility between my-PV and Forstner, more possibilities are opening up for efficient supply from photovoltaics.

Leggi di più...